From initial call out to site to discuss the project, take measurements and supply working drawings for clients to consider and approve.
Once approved a scope of works and plan were put in action to carry out works using a number of trades. Once the main area was cleared of racking in the warehouse, the A/C could be installed using a 17-metre electric scissor lift to suspend the A/C unit from the roof Purlins.
Intern the substructure of the office building could be prepared and installed leaving the way for supplementary trades to carry out their internal works, i.e. plumbing, electrics and joinery.
Armco barrier was put in place around the new QC building to complete the safety aspect already in place to allow stacker trucks to work.
Data cabling, TV Ariel supply and final decoration could then be undertaken prior to delivery of the project on time and under budget.